Duration: 8 months
Start Date: July
End Date: February (tentative)
Work responsibilities:
|
Tasks |
Who |
When |
|
Deans of CLIS and Libraries
agree on charge. |
Preece, Lowry |
July |
|
Dean of Libraries invites
members of JTF/Coordinating Committee. |
Lowry |
July |
|
JTF/CC refines list of
tasks, invites subcommittee members. |
Task Group |
Aug |
|
SERVICES |
|
|
|
Inventory Wasserman Library
services and decide which will be continued or discontinued. |
|
|
|
Determine who will be
responsible for delivering the ongoing services. |
|
|
|
Determine the respective
budgetary responsibilities and budgetary sources. |
|
|
|
COLLECTIONS |
|
|
|
Assess the collections.
|
Collection Mgr LIS Coordinator |
Aug-Sept |
|
Make basic collections
decisions—what stays in Hornbake, what is moved,
what goes to off-site shelving, what is weeded. |
Collection Mgr & CLIS
selector |
Sept |
|
Decide when new purchases
(including serials) are sent directly into the McKeldin collection, instead
of CLIS. |
Task Group |
Start of Classes |
|
Begin planning to unify the
system tables. |
ITD consultant, LIS Coord. |
Sept.-Oct |
|
Work with the “overlap”
list, weeding according to collection management criteria. |
Appropriate group |
Sept-Dec |
|
STACKS SHIFTS AND MOVE |
|
|
|
Determine the shifting
needs and plan for shifting in McK (based on the
list of unique copies). Establish timetable. |
Stacks Mgr |
Sept-Oct |
|
Hire staff to begin
shifting McK Stacks |
|
Oct-Nov |
|
Develop the plan for
moving, including packing, transport, unpacking, system table work, coping
with oversize, and what to do with materials that are charged to patrons,
including timetable for this work |
Task Group |
Nov-Dec |
|
Transfer and shelve the
materials. |
Stacks Staff |
|
Membership
Joint Task
Force/Coordinating Committee
2 CLIS Faculty
K Patterson
C Ruschoff
M White
J Williams, co-chair
T Wray, co-chair
Note: For the purposes of
meeting a quorum of 5 people is necessary.