Work responsibilities: 
Tasks Who When Progress
Deans of CLIS and Libraries agree on charge. Preece, Lowry July Completed.
Dean of Libraries invites members of JTF/Coordinating Committee. Lowry July Completed.
JTF/CC refines list of tasks, invites subcommittee members. Task Group Aug Completed.
SERVICES      
Inventory Wasserman Library services and decide which will be continued or discontinued.      
Determine who will be responsible for delivering the ongoing services.      
Determine the respective budgetary responsibilities and budgetary sources.       
COLLECTIONS      
Assess the collections. Collection Mgr Aug-Sept  
Confer with CLIS faculty and CLIS Library staff. LIS Coordinator  
Create lists of the various LIS Collections, looking at both the overlap and the unique copies.    
Make basic collections decisions—what stays in Hornbake, what is moved, what goes to off-site shelving, what is weeded. Collection Mgr & CLIS selector Sept  
Decide when new purchases (including serials) are sent directly into the McKeldin collection, instead of CLIS. Task Group Start of Classes  
Begin planning to unify the system tables. ITD consultant, LIS Coord. Sept.-Oct  
Work with the “overlap” list, weeding according to collection management criteria. Appropriate group Sept-Dec  
STACKS SHIFTS AND MOVE      
Determine the shifting needs and plan for shifting in McK (based on the list of unique copies). Establish timetable. Stacks Mgr Sept-Oct  
Hire staff to begin shifting McK Stacks   Oct-Nov  
Develop the plan for moving, including packing, transport, unpacking, system table work, coping with oversize, and what to do with materials that are charged to patrons, including timetable for this work Task Group Nov-Dec  
Transfer and shelve the materials. Stacks Staff    